Title 12174 · Code of Ordinances
Sec. 740.107. - Statement of costs to be entered in Street Improvement Lien Book.
Citation: Jacksonville, FL Code of Ordinances § 740.107.
Section: 740.107.
As soon as practicable and within 30 days after the construction or repair of a sidewalk, curb or gutter, the Public Works Department shall prepare a statement of the costs thereof, which statement shall set forth the amount of costs, the date of completion of the work and a description of the parcel of property upon which the lien is claimed. The Department shall transmit the statement of costs to the Tax Collector. The Tax Collector shall enter the information set forth on the statement of costs in a book labeled the Street Improvement Lien Book, which shall be prepared and kept for that purpose and kept open to public inspection during office hours in the Office of the Tax Collector. As soon as practicable after the entries have been made in the Street Improvement Lien Book, the Tax Collector shall cause to be published and mailed or delivered to the owner of each parcel of land along and in front of which the sidewalk, curb or gutter lies, if the lien is for repairs in accordance with Section 740.102 , a notice of the completion of the work and that liens have been entered in the Street Improvement Lien Book. The notice shall contain a legal description of the property against which a lien is claimed for the completed work covered by the notice. One publication of the notice of completion of any and all sidewalk, curb or gutter work provided herein and the fact that liens covering the cost of the work have been entered by the City in the Street Improvement Lien Book published in a newspaper of general circulation in the City shall be sufficient. (Ord. 69-1133-713, § 1; Ord. 70-650-526; Ord. 71-397-181; Ord. 73-1105-829, § 2; Ord. 83-591-400, § 1; Ord. 2012-190-E, § 1) Note— Former § 602.107.