Title 21 · Chapter 21 - STORMWATER MANAGEMENT
Performance security
Section: 21-54
In order to receive final construction approval if work performed under a stormwater permit is not complete, not in accordance with approved plans or is in violation of this chapter, the official, at his discretion, may accept sufficient full performance security guaranteeing the installation and approval of all permitted work. Such performance security shall: Comply with all statutory requirements; be satisfactory in form to the city attorney and appropriate city staff; be in an amount equal to one hundred twenty-five (125) percent of the permittee's contract for the work, subject to approval of the appropriate city staff.
(Ord. No. 89-249, § 2(46-49), 9-28-89)
Cross reference— Sureties of persons dealing with city to be licensed by the state, § 2-231.
Secs. 21-55—21-70. - Reserved.
ARTICLE II. - SANCTIONS; APPEALS; BOARDS
DIVISION 1. - GENERALLY
Secs. 21-71—21-80. - Reserved.
DIVISION 2. - ACTION AUTHORIZED TO MITIGATE VIOLATIONS